Purpose of the Implementation Plan
This plan describes how the NSW Government will implement the NSW Water Strategy from July 2022 to June 2024.
There are more than 40 actions across 7 priority areas in the NSW Water Strategy focused on improving the security, reliability, quality and resilience of the state’s water resources
This implementation plan sets out a program with a strong focus on delivering outcomes and provides a high-level, realistic outline of how the actions in the Strategy will continue to be implemented.
This implementation plan identifies:
- what we will do over the next 2 years under the 42 actions in the NSW Water Strategy
- who the lead agencies and partners are that will work together to deliver the actions.
Each of the actions in the 2022–2024 Implementation Plan contribute to the 7 strategic priorities in the Strategy, which are focused on meeting core objectives based on the NSW Water Management Act 2000. Our set of guiding principles steer the long-term strategic planning for water resource management in NSW, as well as the day-to-day management of the system.
The NSW Water Strategy builds on the progress of the significant water reforms made by the NSW Government to identify emerging program areas required to address water management challenges over the next twenty years.
This implementation plan identifies initiatives that work towards the long-term priorities, objectives and actions of the NSW Water Strategy and is not intended to capture all planned or proposed work or day-to-day ‘business as usual’ activities across the NSW water sector.
Actions taken through this plan contribute to one or more of these core objectives and align with the guiding principles.
Annual reporting on implementation provides transparency and accountability for delivering the Strategy for the NSW community, and will continue. Our first progress report was released in September 2022.
The NSW Water Strategy will be formally evaluated and updated at least every five years.
Timeframes
Following a review of the 2021/2022 NSW Water Strategy Implementation Plan, this 2022 to 2024 plan spans a longer timeframe.
Planning implementation over 2 years enables a more strategic approach to delivery. Longer implementation planning supports the NSW Water Strategy Monitoring, Evaluation and Reporting framework, which requires a baseline evaluation of the strategy after 3 years. It also aligns with implementation planning approaches for the metropolitan and regional water strategies, creating an integrated strategic water management framework for reporting and review.
Implementation actions are shown with indicative timeframes in each year. Additionally, actions from the 2021–2022 implementation plan that have commenced and will be delivered with a revised timeframe have been carried over to this implementation plan.
Delivery of the full strategy will be staged over short, medium and longer-term time horizons. Future actions will be included in subsequent implementation plans as funding is secured and delivery partners identified.
Roles and responsibilities for implementation
Responsibility for water management in NSW is shared between federal, state and local governments, authorities and agencies.
This implementation plan captures actions being undertaken by a number of NSW Government agencies as well as State-Owned Corporations – WaterNSW, Sydney Water and Hunter Water – and independent authorities including the Natural Resources Access Regulator (NRAR) and the NSW Environment Protection Authority (EPA).
A summary of agencies responsible for actions in the 2022 to 2024 implementation plan is shown below.
Local government is a collaborative delivery partner for several actions. The NSW Government is committed to supporting councils deliver outcomes for communities, including through council management and ownership of water supply and sewerage services.
| Organisation | Reference in implementation plan |
|---|---|
| NSW Department of Planning and Environment (now NSW Department of Climate Change, Energy, the Environment and Water) | DPE |
| WaterNSW | WaterNSW |
| Natural Resources Access Regulator | NRAR |
| Department of Regional NSW | DRNSW |
| NSW Environment Protection Authority | EPA |
| NSW Department of Primary Industries | DPI |
| NSW Health | NSW Health |
| Sydney Water | Sydney Water |
| Hunter Water | Hunter Water |
| Local Land Services | LLS |
Summary of actions
Priority 1
Build community confidence and capacity through engagement, transparency and accountability
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| 2 years to June 2024 | DPE WaterNSW NRAR |
– Initial improvements will deliver faster water advice into Planning determinations, with piloted improvements to be tested with targeted stakeholders. | From early 2023 | |
– Improvements to Water Management Act licensing processes (including Water Supply Works and Use approvals, and Water Access Licences) including processes for timely notification of conditions, for targeted stakeholder testing. | From late 2023 | DPE |
| Action plan by December 2022 | DPE |
– governance of engagement processes | ||
– culturally appropriate and place-focused engagement to enhance two-way dialogue with stakeholders | ||
– accessibility of engagement and communications | ||
– expansion and targeting of the monthly Water Engagement Roundup webinar, a ‘Water 101’ fact sheet series to explain water management fundamentals, and monthly departmental eNewsletter to ensure people can see what’s new or changing. | ||
| Annually | DPE |
| Over 2 years to June 2024 | DPE, WaterNSW, NRAR |
| September 2022 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| Ongoing | DPE, WaterNSW |
| By March 2024 | DPE |
| By June 2024 | DPE |
| From December 2022 | DPE |
– Commence a program of publication of existing data on the Sharing and Enabling Environmental Data (SEED) website. | December 2022 | |
| By June 2023 | DPE |
| By June 2024 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| By December 2022 | DPE |
| From June 2023 | DPE |
| By June 2024 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By August 2022 | NRAR |
| By December 2022 | NRAR |
| From September 2022 | NRAR |
| Ongoing | NRAR |
| Ongoing | NRAR |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE, WaterNSW |
| Ongoing | NRAR |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By December 2023 | DPE |
| By December 2023 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By December 2022 | DPE |
| From July 2022 | DPE |
| By December 2022 | DPE |
| By December 2022 | DPE |
| Ongoing | DPE |
| Ongoing | DPE |
| Ongoing | NRAR |
Priority 2
Recognise First Nations/Aboriginal People’s rights and values and increase access to and ownership of water for cultural and economic purposes
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 and ongoing | DPE |
| Ongoing | DPE |
What we will deliver over the next two years
Timing
Responsibility
- Continue the development of the draft Aboriginal Water Strategy, with an initial focus on scoping and co-design of the principles, process and engagement model for consultation on the strategy.
From July 2022
DPE
- Release a draft Aboriginal Water Strategy for public consultation.
By September 2023
DPE
- Finalise the Aboriginal Water Strategy, incorporating feedback received on the draft.
By December 2023
DPE
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| Ongoing | DPE |
| By December 2024 | DPE |
| Ongoing | DPE |
| Ongoing | DPE |
| By June 2024 | DPE |
| By June 2023 | DPE |
| By December 2023 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| Ongoing | DPE |
| By June 2023 | DPE |
| Ongoing | DPE |
| By June 2024 | DPE |
| By June 2024 | LLS |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| From August 2022 | DPE |
| Ongoing | DPE |
Priority 3
Improve river, floodplain and aquifer ecosystem health, and system connectivity
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| Ongoing | DPE |
| By June 2024 | DPE |
| Ongoing | DPE |
| By June 2023 | DPE |
| By June 2024 | DPE |
| By June 2024 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| From December 2023 | DPE, LLS |
| Ongoing | DPE, LLS |
| Commencing 2022 and ongoing | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2025 | DPI, WaterNSW, DPE |
| By June 2023 | DPI |
| By June 2023 and ongoing | DPI |
| By June 2023 | DPI |
| From July 2022 | DPI |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| Ongoing | DPE |
| By December 2022 | DPE |
| Ongoing | DPE |
| By December 2022 | DPE |
| By December 2022 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| By December 2022 | DPE |
| By June 2024 | DPE |
| Ongoing | DPE |
| By June 2023 | DPE |
| By June 2023 | DPE |
| By June 2024 | DPE |
| By June 2024 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| From July 2022 | DPE |
| By December 2022 | DPE |
| From January 2023 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| By June 2023 | DPE |
| No later than June 2025 | DPE |
| Ongoing | DPE |
Priority 4
Increase resilience to changes in water availability (variability and climate change)
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| By June 2024 | DPE |
| Ongoing | DPE, Sydney Water, Hunter Water |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| By June 2024 | DPE |
| By June 2024 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By December 2022 | DPE |
| Ongoing | DRNSW, DPI, DPE |
| By June 2024 | DRNSW, WaterNSW, DPE |
| By June 2024 | DRNSW, DPE |
| By June 2023 | DPE |
| By June 2023 (Greater Sydney) By December 2023 (Lower Hunter) | Hunter Water, Sydney Water |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2024 | DPE |
| By June 2023 | DPE, Sydney Water |
| By June 2023 | DPE |
| June 2023 | DPE |
| Ongoing | DPE |
| By June 2024 | DPE |
| Ongoing | DPE |
Priority 5
Support economic growth and resilient industries within a capped system
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| Ongoing | DRNSW, DPE |
| By June 2023 | DRNSW, DPE |
| By June 2023 | DRNSW, DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2024 | DPI, DRNSW |
| Ongoing | DPI |
| Ongoing | DPE |
| By June 2024 | Hunter Water |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| Ongoing | DPE, WaterNSW |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| From June 2022 | DPE |
| From June 2022 | DPE, Sydney Water, Hunter Water |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By September 2023 | DPE |
Priority 6
Support resilient, prosperous and liveable cities and towns
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By September 2022 | DPE |
| Ongoing | Sydney Water, Hunter Water |
| By June 2023 | DPE |
| By July 2023 | DPE |
| By June 2024 | Hunter Water |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| Ongoing | DPE, EPA, NSW Health |
| Report annually | DPE, EPA, NSW Health |
| Ongoing | DPE, EPA, NSW Health |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By December 2022 | DPE, Sydney Water, Hunter Water, WaterNSW, NSW Health, EPA |
– co-design with the local government sector a new regulatory and assurance framework to ensure regulation is modern, risk-based and outcomes focused | ||
– co-create with the training, local government and water sectors a plan to address barriers for water operators | ||
– through pilot initiatives, investigate opportunities to improve collaboration between local water utilities and evaluate their effectiveness | ||
– through pilot initiatives, investigate and evaluate new approaches to support local water utilities by State-Owned Corporations (SOCs) | ||
– analyse the financial needs and capacity of diverse local water utilities to meet their service obligations in their local circumstances, to inform future policies | ||
– improve support for councillors as the governance and decisions-makers of local water utilities. | ||
| From July 2022 | DPE, WaterNSW, NSW Health, EPA |
– new strategic planning provisions for local water utilities through a staged approach | ||
– structural changes to support the department’s advisory and regulatory roles for local water utilities | ||
| From October 2022 | DPE, WaterNSW, NSW Health, EPA |
– 2 year Skills and Training Action Plan to address the water technical skill shortages of regional and remote councils | ||
– investigate options for alternative funding arrangements of local water utilities | ||
– continued support for councillors as the governance and decisions-makers of local water utilities | ||
– continue programs to reduce risks through collaboration, sharing of information and leverage of the capabilities of WaterNSW. |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| From July 2022 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| Ongoing | NSW Health |
| Ongoing | NSW Health |
| Ongoing | NSW Health |
| Ongoing | NSW Health |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| Ongoing | DPE, Sydney Water, Hunter Water |
| Ongoing | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| By June 2023 | DPE, NSW Health, EPA |
| By June 2024 | DPE |
| By June 2023 | DPE |
| By June 2024 | DPE |
| From July 2022 | DPE |
| By June 2023 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | DPE |
| By June 2024 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By December 2023 | DPE |
| By June 2023 | DPE, Sydney Water |
| From July 2022 | DPE |
| By July 2023 | Sydney Water |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2023 | IPART |
| By June 2023 | IPART |
| By June 2023 | IPART |
| By December 2022 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| Ongoing | EPA |
| By July 2023 and ongoing | Sydney Water, Hunter Water |
Priority 7
Enable a future focused, capable and innovative water sector
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By December 2022 | DPE |
| By June 2023 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By September 2024 | DPE |
| By December 2023 | DPE |
| What we will deliver over the next two years | Timing | Responsibility |
|---|---|---|
| By June 2024 | DPE |
| By June 2024 | DPE |
| By June 2023 | DPE |
| Ongoing | DPE |
Implementation Plan 2022-24
Download the Implementation plan 2022-24
Previous Implementation Plan 2021-22
Our first implementation plan for the NSW Water Strategy was released in September 2021. A one year plan, the majority of actions in this implementation plan have now been completed. Find out more about how we have delivered these actions in the 2021-2022 Annual progress report.