Billabong Creek Regulators

Delivering new regulators along Billabong Creek.

Hartwood Weir Billabong Creek

About the project

The NSW Government is replacing 2 ageing weirs along Billabong Creek at Hartwood and Wanganella with new regulators. 

The existing weirs, which were built in the early 20th century, are in poor condition, restrict fish movement and limit regulated flows through the Yanco Creek system, leading to inefficient delivery of water for the environment and water users. 

The new regulators will be fully automated, remotely operated and will include vertical-slot fishways, allowing water to be delivered more efficiently through the creek system and improving native fish passage.

Work to set up the sites started in April 2026. Construction will continue throughout the year with practical completion scheduled for December 2026. Commissioning and handover of the regulators is scheduled for early 2027.

Replacing the Billabong Creek regulators is part of a range of infrastructure works being undertaken as part of the Yanco Creek Modernisation Project. This project is one of 5 projects being delivered as part of the NSW Government's Sustainable Diversion Limit Adjustment Mechanism Acceleration Program, with funding from the Australian Government.  

Project status

Construction is now underway at both the Hartwood and Wanganella regulator sites. 

The green light to proceed with replacing the 2 weirs was granted following an extensive consultation process including public exhibition of the Environmental Impact Statement in November 2024.

The department’s Water Group awarded the contract to Abergeldie Complex Infrastructure following a competitive tender process.

About the new regulators

The new regulators will be located along Billabong Creek approximately 100 metres downstream of the old Hartwood and Wanganella weirs. The existing weirs will be removed after the new regulators are installed.

The construction process for the new regulators is designed to minimise impacts on water flowing through Billabong Creek, allowing water to continue to pass through for irrigation, town water and environmental purposes.

During the construction period there will be increased truck traffic along local roads including the Cobb Highway between Deniliquin and Wanganella and Conargo Road between Deniliquin and Jerilderie.

Access to the area around the new Wanganella regulator site will be restricted while work is underway, however access to Wanganella Recreation Reserve further upstream and downstream of the work site will remain open.

Regulator designs

View the designs of the new regulators below:

Project timeline

  1. February 2026

    Planning approval

  2. April 2026

    Site establishment and in-stream pre-construction works

  3. May 2026

    Construction of the regulators and fishways and installation of new powerlines commences

  4. December 2026

    Practical completion of regulators 

  5. February 2027

    Demolition of existing weirs

  6. March 2027

    Commissioning and handover of regulators

Environmental Impact Statement

The Environmental Impact Statement (EIS) for replacing the Billabong Creek regulators went on public exhibition from 1 November to 28 November 2024.

The EIS outlined:

  • the proposed construction and operational footprint of two new Billabong Creek regulators
  • findings from the environmental and cultural heritage assessments
  • proposed steps to be taken to avoid or reduce impacts during construction and operation.

The public exhibition of the EIS allowed community members, stakeholders and businesses the opportunity to learn more and help shape this important infrastructure project.

See documents relating to the determination of the Billabong Creek EIS, including the Response to Submissions below.

Assessment documents

Application 

Planning Secretary’s Environmental Assessment Requirements (SEARs)

Environmental Impact Statement (EIS)

Agency advice on the Environmental Impact Statement

Response to submissions

Agency responses to submissions report

Additional information 

Agency responses to additional information report

Approval documents

Post approval documents

Notifications
Management plans and strategies
Other documents

About vertical slot fishways

The new regulators will feature vertical slot fishways to provide a passageway to help fish migrate safely upstream and downstream. 

Vertical slot fishways consist of a concrete channel bypassing a regulator or weir.

Fishways enable native fish to migrate to complete key life stages and to avoid drying habitats during drought.

An example of a vertical slot fishway is shown below: 
 

Conceptual layout of a vertical slot fishway
Example of vertical slot fishway

To learn more about vertical slot fishways, visit the NSW Department of Primary Industries Fisheries website.

Translation services

If you need help understanding this information, please contact the Translating and Interpreting Service on 131 450 and ask them to call us on 1800 801 738.

Contact us

For questions, feedback or complaints about the Billabong Creek regulator works:

Your personal information will be handled in line with the department’s privacy statement.

Please note:

(a) the Complaints Register may be forwarded to government agencies, including the Department and its representatives (including independent appointments such as the environmental representative for the regulators approved by the Planning Secretary), to allow them to undertake their regulatory duties

(b) by providing personal information, you authorise the department to provide that information to government agencies 

(c) the personal information you provide is voluntary 

(d) you have the right to contact government agencies to access personal information held about you and to correct or amend that information (Collection Statement).