Extended weekend working hours
The NSW Government is contacting residents living close to the Wanganella regulator site seeking their agreement for extended weekend working hours to occur during construction. Find out more
About the project
The NSW Government is replacing 2 ageing weirs along Billabong Creek at Hartwood and Wanganella with new regulators.
The existing weirs, which were built in the early 20th century, are in poor condition, restrict fish movement and limit regulated flows through the Yanco Creek system, leading to inefficient delivery of water for the environment and water users.
The new regulators will be fully automated, remotely operated and will include vertical-slot fishways, allowing water to be delivered more efficiently through the creek system and improving native fish passage.
Work to set up the sites is scheduled to start in early 2026. Construction will continue throughout the year with practical completion scheduled for December 2026. Commissioning and handover of the regulators is scheduled for early 2027.
Replacing the Billabong Creek regulators is part of a range of infrastructure works being undertaken as part of the Yanco Creek Modernisation Project. This project is one of 5 projects being delivered as part of the NSW Government's Sustainable Diversion Limit Adjustment Mechanism Acceleration Program, with funding from the Australian Government.
Project status
The green light to proceed with replacing the 2 weirs has been granted following an extensive consultation process including public exhibition of the Environmental Impact Statement in November 2024.
The department’s Water Group has awarded the contract to Abergeldie Complex Infrastructure following a competitive tender process.
Work to set up the sites is scheduled to start in early 2026 with construction continuing throughout the year.
Location map of new regulators
The new regulators will be located along Billabong Creek approximately 100 metres downstream of the old Hartwood and Wanganella weirs. The existing weirs will be removed after the new regulators are installed.
The construction process for the new regulators is designed to minimise impacts on water flowing through Billabong Creek, allowing water to continue to pass through for irrigation, town water and environmental purposes.
During the construction period there will be increased truck traffic along local roads including the Cobb Highway between Deniliquin and Wanganella and Conargo Road between Deniliquin and Jerilderie.
Access to the area around the new Wanganella regulator site will be restricted while work is underway, however access to Wanganella Recreation Reserve further upstream and downstream of the work site will remain open.
Regulator designs
View the designs of the new regulators below:
Project timeline
-
February 2026
Planning approval
-
Early April 2026
Site establishment and in-stream pre-construction works
-
Late April 2026
Construction of the regulators and fishways and installation of new powerlines commences
-
December 2026
Practical completion of regulators
-
February 2027
Demolition of existing weirs
-
March 2027
Commissioning and handover of regulators
Environmental Impact Statement
The Environmental Impact Statement (EIS) for replacing the Billabong Creek regulators went on public exhibition from 1 November to 28 November 2024.
The EIS outlined:
- the proposed construction and operational footprint of two new Billabong Creek regulators
- findings from the environmental and cultural heritage assessments
- proposed steps to be taken to avoid or reduce impacts during construction and operation.
The public exhibition of the EIS allowed community members, stakeholders and businesses the opportunity to learn more and help shape this important infrastructure project.
See documents relating to the determination of the Billabong Creek EIS, including the Response to Submissions below.
Attachments and resources
- Billabong Creek Regulators EIS - Summary
- Billabong Creek Regulators EIS - Main report
- Appendix A-SEARs compliance table
- Appendix B-Detailed maps and plans
- Appendix C-Statutory compliance
- Appendix D-Environmental risk assessment
- Appendix E- Consultation report
- Appendix F-Mitigation measures
- Appendix G-Hydrology assessment
- Appendix H-Flood impact assessment
- Appendix H-Sub App D-Hartwood Hydraulic Modelling Report
- Appendix H-Sub App E-Wanganella Hydraulic Modelling Report
- Appendix I-Groundwater assessment report
- Appendix J-Geomorphology assessment report
- Appendix K-Surface WQ & aquatic ecology assessment report
- Appendix L-Terrestrial flora and fauna – BDAR
- Appendix M - ACHA - Main Redacted-with cover
- Appendix M - ACHA Appendices redacted_with cover
- Appendix N-Non-Aboriginal heritage assessment report
- Appendix O-Land use assessment report
- Appendix P-Traffic and access impacts assessment
- Appendix Q-Noise and vibration impact assessment
- Appendix R-Social impact assessment
- Appendix S-ESD report and CRA report
- Appendix T-Contamination assessment
- Appendix U - Draft Yanco Creek System Operations Plan
- Request RTS Letter
- Appendix F - ACHA Volume 2 Redacted
- Appendix F - ACHA Main Report Redacted
- Billabong Creek Regulators - Submission Report
- Appendix D - Revised BDAR
- Appendix H - Review of hydrologic models
- Appendix G - project entitlement sizing
- Appendix C - Additional Hydrology & flooding figures
- Appendix E - Contamination Report
- Appendix B - Additional drawings
- Appendix A - Updated mitigation measures
- DPIRD response_Billabong Creek EWater Regulators_EIS
- NSW DCCEEW Water Group response
- Billabong Creek Enviro Water Response
- BCS Response - Billabong Creek Regulators EIS
- HeritageNSW_EH_EIS_SSI-50831979_HMS 7739
- NSW SES Billabong Creek Environmental Water Regulators
- WaterNSW Advice_Billabong Creek_RFI
- Billabong Creek Env Water Reg - SSI-50831979 - RFI
- HNSW ACH - RtS - Billabong Creek - SSI-50831979
- Billabong Creek EIS DSNSW
- MDBA response
- EPA Response Billabong Creek
- HNSW ACH - Billabong Creek Weirs - SSI-50831979
- SSI-50831979 - TfNSW SF2024_201116
- WaterNSW advice_SSI 50831979
- NPWS Response - SSI 50831979 Billabong Ck
- Billabong Creek Regulators SSI50831979 EIS
- NSW SES Response Billabong Creek
- WaterNSW Advice - BillabongCreek_RTS
- NPWS Response- RTS Billabong Creek Regulators
- HNSW ACH - RtS - Billabong Creek - SSI-50831979
- Billabong Creek Water Regulators Response Letter
- DCCEEW Water - Billabong Creek Regulators - RTS
- EPA - Billabong Creek - SSI 50831979 - RTS
- RD Response - Billabong Creek Regulators RTS_
- Response to Submissions - SSI-50831979
- DPIRD Fisheries - RtS - SSI-50831979 - Billabong Creek EWR
- ERC RtS - DCCEEW Billabong Creek Regulators
- DPIRD response - Billabong Creek EWater Regulators RtS
- 250716 - Request for Additional Information
- RFI Report for Billabong Ck EIS_V1.01
- Billabong Creek Regulators - ACHA Final RFI Redacted
Extended weekend working hours
The NSW Government is seeking agreement from residents living close to the Wanganella regulator site for extended weekend working hours to occur during construction.
Agreement is being sought for the contractor to carry out construction activities from 7am to 6pm on some weekends when required. These activities may include the use of heavy machinery exceeding noise management levels for some residents near the area where the works are taking place.
These residents will experience typical noise levels of between 30-50dB during the extended weekend working hours, with short periods of peak noise up to 62db. For context, a running refrigerator is around 50 dB and a normal conversation is around 60-70dB.
The Water Group is sending letters to affected residents with further information.
If you receive a letter, you can agree to the extended weekend working hours:
- online, by completing the online agreement form
- by phoning 1800 801 738 (quoting the reference number on your letter)
- by emailing water.enquiries@dcceew.nsw.gov.au with the subject line Billabong Creek regulators extended weekend working hours agreement
- include your name, address, phone number and provide your consent/agreement for extended weekend working hours to occur
- by completing the downloadable agreement form and:
- emailing it to water.enquiries@dcceew.nsw.gov.au
- posting it to:
Billabong Creek Regulators Project
NSW Department of Climate Change, Energy, the Environment and Water
Locked Bag 5022
Parramatta NSW 2124
If you are unsure if you need to complete the agreement form, call or email us using the contact details below.
About vertical slot fishways
The new regulators will feature vertical slot fishways to provide a passageway to help fish migrate safely upstream and downstream.
Vertical slot fishways consist of a concrete channel bypassing a regulator or weir.
Fishways enable native fish to migrate to complete key life stages and to avoid drying habitats during drought.
An example of a vertical slot fishway is shown below:
To learn more about vertical slot fishways, visit the NSW Department of Primary Industries Fisheries website.
Translation services
If you need help understanding this information, please contact the Translating and Interpreting Service on 131 450 and ask them to call us on 1800 801 738.
Contact us
For questions, feedback or complaints about the Billabong Creek regulator works:
- call: 1800 801 738
- email: water.enquiries@dcceew.nsw.gov.au
- mail:
Billabong Creek Regulators Project
NSW Department of Climate Change, Energy, the Environment and Water
Locked Bag 5022
Parramatta NSW 2124
Your personal information will be handled in line with the department’s privacy statement.
Please note:
(a) the Complaints Register may be forwarded to government agencies, including the Department and its representatives (including independent appointments such as the environmental representative for the regulators approved by the Planning Secretary), to allow them to undertake their regulatory duties
(b) by providing personal information, you authorise the department to provide that information to government agencies
(c) the personal information you provide is voluntary
(d) you have the right to contact government agencies to access personal information held about you and to correct or amend that information (Collection Statement).