Mundowy Lane Upgrade Project

Upgrading Mundowy Lane to reduce overtopping.

Mundowy Lane

About the Mundowy Lane upgrade project

Mundowy Lane is an important arterial road crossing Beavers Creek and the Murrumbidgee River, near the township of Collingullie. The road is owned and maintained by Wagga Wagga City Council.

In addition to being a constraint to river flows, the road has been inundated on several occasions over recent years by flows from the Murrumbidgee River system.

Flows of 35,000 ML/day (5.51 m) at Wagga Wagga see water beginning to cross over the southern section of the road, requiring traffic control and reducing traffic to a single lane. At 44,000 ML/day (6.44 m) at Wagga Wagga, the road is closed causing detours of up to 50 km for local traffic.

This negatively impacts the communities relying on the road to get to work, get their children to school and manage their business/farming operations.

Upgrading this section of road will protect against high river flows and provide substantial benefit to the local community.

Project scope

The southern section of Mundowy Lane will be upgraded preventing inundation during flows up to 45,000 ML/day at Wagga Wagga.

New culverts will be placed under the roadway, with minor raising over 2 sections of approximately 400 m in length. This will allow the passage of higher flows through the culverts, reducing the risk of damage to the road and mitigating impacts to adjacent properties.

Works to ensure access to properties during flows up to 45,000 ML/day will also be provided.

The project is fully funded by the Australian Government with practical completion scheduled for December 2026.

Project benefits

The benefits of the project will include:

  • improved vehicle access and road safety during high flows
  • less overtopping of the road, resulting in less disruption to local communities
  • eliminating the need for traffic control and lane closure with flows up to 45,000 ML/day
  • less servicing and maintenance of the road and road verges.

Current status

The department’s Water Group is leading the delivery of the project with the involvement of Wagga Wagga City Council.

All planning and approval activities for the project are now complete. This included developing an Aboriginal Cultural Heritage Assessment Report in partnership with Traditional Owners, undertaking ecological and environmental studies, completing site surveys and carrying out geotechnical investigations and hydraulic modelling to inform design.

The Water Group has finalised the detailed designs of all the culverts and awarded the construction contract to Fulton Hogan after a competitive tender process.

Site mobilisation is underway with construction expected to begin in mid-June. 

Once construction starts, local communities will experience changed traffic conditions. Single lane side tracks will be put in place around the culvert bays with portable traffic lights deployed to control traffic flow. Reduced speed limits will also be in place during the works for the safety of road users and the construction team.  

These changed traffic conditions may vary over time as the work progresses. 

Once construction and commissioning of the road upgrade is complete, Wagga Wagga City Council will continue as the asset owner.

Project timeline

  1. March 2026

    Contract awarded

  2. June 2026

    Site established
    Construction commences

  3. December 2026

    Practical completion of road upgrade

  4. January 2027

    Finalise works

  5. February 2027

    Handover to Wagga Wagga City Council

Stakeholder and community engagement

The Water Group is committed to building and maintaining respectful, trusted and collaborative relationships with our communities and stakeholders to ensure water infrastructure projects achieve the best possible outcomes.

We have engaged extensively with surrounding landholders and Wagga Wagga City Council throughout the project’s assessment phase and their feedback helped inform the concept and final design of the road upgrade.  We also sought feedback from the community more widely at drop-in sessions held in Wagga Wagga and Gundagai in July 2025. 

In response to stakeholder feedback, the Water Group revised the initial design to incorporate 9 additional culverts in key flow areas, allowing additional flow capacity under the road and reducing the risk of blockage. The addition of these culverts brings the total number of new culverts being installed along the road to 24.

We will continue to work closely with affected landholders and other stakeholders to understand what needs to be done to deliver the road upgrade, while minimising local impacts, and will continue to keep local communities informed as the project progresses.

Business information 

The Water Group hosted a session in Wagga Wagga in August 2025 to provide businesses with information about upcoming tenders and the range of goods and services needed for the delivery of the Mundowy Lane upgrade, Mundarlo Bridge replacement and Werai Forest projects. Download a copy of the presentation and sign up for the Water Group’s water infrastructure business register via the links below.

Documents

Date Document name
27 November 2025 Review of environmental factors: Mundowy Lane (PDF, 7.17 MB)
01 August 2025 Business information session, Wagga Wagga (PDF, 4.56 MB)
3 men in high vis

Register to be notified about potential business opportunities resulting from our water infrastructure projects.

Subscribe or contact us

Sign-up for email updates.

Subscribe now

Contact us

For more information call us on 1300 081 047 or email us at water.enquiries@dcceew.nsw.gov.au